2021 Stormwater Pond Maintenance Project

Overview

The City is implementing its 2021 stormwater pond maintenance projects (see project map below). These project locations were chosen based on the comprehensive survey and subsequent prioritization of the City’s entire network of stormwater ponds completed in fall of 2020. This is the first project in what is anticipated to be a robust annual stormwater pond maintenance program. This work will be paid for utilizing the Surface Water Management Fees collected with utility bills and new developments, with no additional cost to property owners.

The general scope of work includes removing obstructions to access the ponds, cleaning out accumulated sediment, stabilizing eroded areas, repairing storm pipes and structures, and restoring the disturbed areas.  All work will be performed within city owned easements.  The 2021 projects are currently in design phase with construction anticipated late winter 2021/early winter 2022, with final restoration occurring in spring 2022.

Access to the ponds will be different at each location and the City will work with adjacent property owners ahead of and during construction to communicate the scope of work. It is likely that some trees and other vegetation may need to be removed in order to access each pond. 

If you have any questions about this program or the particular work at these locations, please contact the City’s Water Resources Coordinator, Matt Unmacht at MUnmacht@ci.chanhassen.mn.us or at 952-227-1168.

2021 Stormwater Pond Maintenance Map

  1. Matt Unmacht

    Water Resources Coordinator
    Phone: (952) 227-1168

NotifyMeKaren_thumb.png Opens in new window
Click on the Notify Me button to sign up with your email and/or cell phone number to receive project updates. The information provided will be general in nature, such as proposed project schedule and upcoming construction activities. Contact Stacy at 952-227-1162 or by email for assistance.

Project Updates

Come back to this page for project updates or click on the “Notify Me” icon to have updates automatically sent to you by email and/or text message.

October 27, 2021

Letters with more specific information, will be mailed to adjacent property owners soon.

Schedule
Bid OpeningOctober 27, 2021
Tentative Council ApprovalNovember 8, 2021
Construction StartTentatively Scheduled for Last Week of November, 2021
Construction EndSpring 2022